School Building Committee, May 11, 2016
the recording · 0:43 long, about 4,706 words spoken · captions carried this meeting poorlylunenburgbudgetproject.org — written by the Lunenburg Budget Project, an independent tool for residents. Not affiliated with the Town of Lunenburg, the School Committee or the school district. The data this page is computed from: /data/recording-minutes/school-building-committee/2016.json
The town has published neither minutes nor an agenda for this meeting. The recording is the only record, and what follows is a guide to it.
The short version
- ▶ 10:16The School Building Committee approved amendment number 11 to the architect contract, which reconfigures the front sports fields.
- ▶ 29:40The committee approved a change replacing a retaining-wall fence with boulders and plantings, with a credit for the fence.
- ▶ 32:15The committee agreed to keep the overflow parking area as designed, a grass area, with no financial impact.
- ▶ 10:30Members heard that a Verizon strike was delaying phone lines and elevator inspection ahead of move-in.
- ▶ 1:18The committee reviewed monthly design and construction invoices and approved the prior minutes as amended.
Why it matters — our reading
- The votes change the finished layout of the new school's fields and grounds, and they use the project's construction budget, which is paid for by taxpayers.
- Delays to phone lines and elevator inspection could affect when the building is ready for students and staff to move in.
Watch next
- Later committee minutes, for the change order log and whether phone service and elevator inspection are finished before move-in.
athleticscapitalcontracts and unionsfacilitiesmsbatechnology
Votes
- ▶ 10:16Approve amendment number 11 (architect contract to reconfigure the sports fields)passed
- ▶ 29:40Approve the retaining wall change replacing the fence with boulders and plantingspassed
And 2 procedural: approve the minutes as amended (attendance correction) (▶ 0:55); adjourn (▶ 43:48).
The money
- ▶ 1:18Monthly invoices for design and construction
Monthly invoices were reviewed, including construction, architect and testing services.
as heard:1 million one hundred nine thousand nine sixty eighty fivefifty two thousand five hundred85,000 126 20two hundred twenty dollars
- ▶ 2:24Snow blower purchase
A snow blower was bought as part of the project.
as heard:two thousand 559
- ▶ 4:15Amendment 11 landscape architect field redesign
Contract amendment to reconfigure field sizes and move lighting.
as heard:2244 dolls
- ▶ 12:58Elevator contractor to operate cab during move-in
Hiring the elevator contractor for three days was cheaper than the alternative.
as heard:5476 dollars
- ▶ 21:43Retaining wall change replacing fence
Boulders and plantings replace the fence, with a credit for the fence.
as heard:ten thousand thirty nine dollarsnineteen thousand
- ▶ 36:30Furniture recycling contract payment terms
Discussion of a down payment and payment split for the recycling vendor.
as heard:ten-thousand-dollar contractssix thousand
Settled without a vote
- ▶ 32:15Committee agreed to keep the overflow parking area as designed, a grass area, with no financial impact.
Documents and exhibits
The town’s minutes
The town has not published minutes for this meeting.
State law asks minutes to list the documents and exhibits used at a meeting (M.G.L. c.30A §22(a)). Names from the recording are the caption model’s hearing; the two sides are matched by name, by script, so a document named two different ways can be missed. A place to look, not a finding.
Where the time went
Minutes of recording by subject, from the topic spans below. A topic with two subjects counts toward both.
- facilities33 min · 76%
- capital9 min · 21%
- technology8 min · 19%
- athletics7 min · 15%
The whole meeting, in order
- ▶ 0:09Minutesvoted · 1:09 long
- ▶ 1:18Monthly invoicesinformational · 2:33 long · capital
- ▶ 3:51Amendment 11 field reconfigurationvoted · 6:39 long · athletics, capital
- ▶ 10:30Change order log and Verizon strike delayinformational · 8:20 long · facilities
- ▶ 18:50Concession stand retaining wall changevoted · 11:15 long · facilities
- ▶ 30:05Overflow parking areadecided to keep as grass · 2:31 long · facilities
- ▶ 32:36Furniture moving and recyclinginformational · 2:52 long · facilities
- ▶ 35:28Construction progress and technologyinformational · 8:20 long · facilities, technology
- ▶ 43:48Adjournmentvoted · 0:12 long
What the captions could not carry
- Vote counts were not stated
- Several stretches (around 187-231, 2235-2329) are garbled
- Speakers not identified
These are ours, and they are not the record
OUR MINUTES OF A RECORDING, written by a language model from machine captions. Two derived layers stand between this file and the meeting. Cite the video at the timestamp, never this file. Figures are as heard and may be wrong; names may be wrong; where the town published minutes, those are the record.