What was said

Zoning Board of Appeals, January 9, 2019

the recording · 0:40 long, about 5,261 words spoken · captions carried this meeting moderately well

The town published an agenda for this meeting. No minutes have been published; the recording is the only record, and what follows is a guide to it.

The short version

  1. ▶ 37:46The Zoning Board of Appeals approved a special permit for a ground-mounted solar array that would not meet the 25-foot side yard setback.
  2. ▶ 37:46Approval carries a condition of a solid fence and pine trees on the line with the abutters as a buffer.
  3. ▶ 38:31The permit is subject to applicable licenses and regulations and periodic review, must be recorded at the Registry of Deeds, and lapses in two years unless construction begins.
  4. ▶ 21:48Abutters spoke in support or without objection, asking about screening, deer-resistant plantings and notice if the plan changes.
  5. ▶ 35:44A resident asked about a rooftop fallback; the board said a roof system could be built by right.

Why it matters — our reading

  • The decision shows how a setback exception for home solar is weighed: the board allowed a closer side line in exchange for a screening condition protecting neighbors.
  • The permit lapses if construction does not start within two years, so the array is not guaranteed to be built.

Watch next

  • The permit must be recorded at the Registry of Deeds and lapses in two years unless construction has started.

planning and zoningpublic comment

Present: Hal Greville (chair); James feza Keisuke (member); Paul Doherty (member); David Blatt (member); Pat Callahan (member); Lisa (staff (absent, unwell)). Names are the caption model’s hearing and may be wrong.

Votes

  1. ▶ 37:46Approve the special permit for the ground-mounted solar array with a condition of a solid fence and pine trees on the line with the abutters as a buffer.passed

And 1 procedural: adjourn. (▶ 39:56).

The money

Nothing touching money was heard beyond the transfers.

Settled without a vote

  • ▶ 38:31Special permit granted, subject to compliance with all applicable licenses and regulations and periodic review; must be recorded at the Registry of Deeds, and lapses in two years unless construction has commenced.

Documents and exhibits

The town’s minutes

The town has not published minutes for this meeting.

Heard in the recording

  • ▶ 1:26Special permit applicationapplication or permit, shown
  • ▶ 5:21Letter from New England clean energyletter or email, shown
  • ▶ 6:07System key specifications and plot planplan or drawing, shown
  • ▶ 5:01Zoning bylaw sectiondraft policy or bylaw, shown

State law asks minutes to list the documents and exhibits used at a meeting (M.G.L. c.30A §22(a)). Names from the recording are the caption model’s hearing; the two sides are matched by name, by script, so a document named two different ways can be missed. A place to look, not a finding.

Public comment

  1. ▶ 21:48No opposition to the plan as filed; wants notice and a chance to be heard if it changes; asked about boulders and vegetation affecting the array and about the earlier tree-removal permission. — Jonathon Heinberg, as heard, future neighbor at 331 Northfield Road
  2. ▶ 26:00No objection; called it the best location on the lot and urged the board to get the other abutter's opinion. — jayjay Cote, as heard, resident, 371 Northfield Road
  3. ▶ 26:52In favor; asked for the side-line dimensions and for deer-resistant vegetation along the line. — 379 Northfield Road resident, as heard, abutter
  4. ▶ 35:44A resident asked whether the applicant could go back to a rooftop plan if this were denied; the board said a roof system could be built by right.

Where the time went

Minutes of recording by subject, from the topic spans below. A topic with two subjects counts toward both.

The whole meeting, in order

  1. ▶ 0:00Hearing procedure and reading of the application, findings and supporting letterinformational · 6:26 long · planning and zoning
  2. ▶ 6:27Applicant's presentation and board questions on siting, height, setbacks, screening and battery backupinformational · 14:30 long · planning and zoning
  3. ▶ 21:26Public comment from abuttersinformational · 7:44 long · public comment, planning and zoning
  4. ▶ 29:11Applicant's responses on boulders, fence, vegetation; question on rooftop fallbackinformational · 8:09 long · planning and zoning
  5. ▶ 37:20Deliberation, motion and approval with buffer condition; permit appeal and recording terms readvoted · 2:35 long · planning and zoning
  6. ▶ 39:56Adjournmentvoted · 0:24 long

What the captions could not carry

  • Vote count on the permit was not stated; only 'aye' and the chair's statement that it passed.
  • Names of the mover and seconder of the motion are not audible.
  • Some measurements (setbacks of 100 or 150 feet) were garbled in the captions.
  • Adjournment vote result not stated beyond 'aye'.

These are ours, and they are not the record

OUR MINUTES OF A RECORDING, written by a language model from machine captions. Two derived layers stand between this file and the meeting. Cite the video at the timestamp, never this file. Figures are as heard and may be wrong; names may be wrong; where the town published minutes, those are the record.