FY2025 capital plan
lunenburgbudgetproject.org — written by the Lunenburg Budget Project, an independent tool for residents. Not affiliated with the Town of Lunenburg, the School Committee or the school district. The data this page is computed from: /data/topics/capital-fy2025.json
10 of 35 capital requests were funded, 37.9% of the dollars requested.
From ranked to funded
1Ranked by the Capital Planning Committee
35 requests · $3,474,768
Capital Planning Committee — FY2025 capital requests by department, final (workbook)
25 requests ranked here were not in it
2In the Town Manager’s preliminary plan
10 requests · $1,317,120
Town Manager — FY2025-FY2034 preliminary capital plan presentation
↓
3Funded at Town Meeting
10 requests · $1,317,120
Town of Lunenburg — FY2024 annual town report (Article 6, May 2024)
What it means: What the Town Manager put in the first plan is what was funded, request for request.
10 of 35 requests were funded, 37.9% of the dollars; the first plan held 10.
What it means: The rest was not cancelled by this vote; the road-back grid on the hub shows which requests came back.
10
funded
35
ranked requests
37.9%
of the requested dollars funded
10
in the first plan
Every request, in rank order
- 1Public Safety Radio System - Replace update obsolete equipment- Phase 2FireFire$315,263
- 2Town Wide Keying, Card Access & Alarm System UpgradesFacilitiesFacilities$185,000
- 3Marked Police Vehicle, replacement for K9 cruiserPolicePolice$92,211
- 4THES, ADA Study for Renovations and Assessment and Schematic DesignSchoolsSchools$275,000
- 5Marked Police Vehicle, replacement for Traffic vehiclePolicePolice$73,627
- 6Library Security Cameras Phase IITIT$36,000
- 7Northfield Culvert (Kelly's Pond) ConstructionPublic WorksPublic Works$200,000
- 8THES, Installation of 3M Window Safety FilmSchoolsSchools$33,569
- 9Security Camera Upgrades at Town BuildingsITIT$36,450
- 10Parks, Wallis Park Basketball and Tennis CourtsFacilitiesFacilities$70,000
The highest-ranked request left unfunded
11MILO Advanced Training Simulation SystemPolicePolice$33,910- 12Drainage Swales at 181 Reservoir RoadPublic WorksPublic Works$75,000
- 13District, Dump Truck with PlowSchoolsSchools$74,500
- 14DPW Garage Floor RepairsFacilitiesFacilities$60,000
- 15North Cemetery Expansion AreaPublic WorksPublic Works$50,000
- 16DPW, Partial Roof ReplacementFacilitiesFacilities$65,000
- 17Air Compressor and AccessoriesPublic WorksPublic Works$30,000
- 18Parks McNally ParkFacilitiesFacilities$50,000
- 19LMHS Turf Field, Site Survey & Drainage ImprovementsSchoolsSchools$200,000
- 20Lunenburg Primary School, Designer Services, Playground EquipmentSchoolsSchools$30,000
- 21Lunenburg Primary School, Classroom AC units (phase II)SchoolsSchools$160,000
- 22Parks, Marshall Pond TreatmentFacilitiesFacilities$50,000
- 23Front End Loader with PlowPublic WorksPublic Works$275,000
- 24Public Safety Building 2nd Floor Space EngineeringFacilitiesFacilities$35,000
- 25Cemetery, Headstone RestorationPublic WorksPublic Works$38,500
- 26Lunenburg Primary School, Feasibility Study for Entry & Drive Way ExpansionSchoolsSchools$30,000
- 27Ritter Building, Rear Stair Cover AccessFacilitiesFacilities$35,000
- 28Drainage Improvements on Laurel LanePublic WorksPublic Works$250,000
- 29Primary, Installation of 3M Window Safety FilmSchoolsSchools$38,120
- 30MSHS, Installation of 3M Window Safety FilmSchoolsSchools$42,618
- 31Cemetery EnhancementsPublic WorksPublic Works$20,000
- 32Senior Center, Parking Lot DesignFacilitiesFacilities$35,000
- 33Ritter Building, Floor Covering Replacement Vertex Item #14FacilitiesFacilities$65,000
- 34Ritter Building, Painting, Vertex Year 2 Items #15-16FacilitiesFacilities$65,000
- 35North Cemetery New Stone WallPublic WorksPublic Works$350,000
What it means: Read down the list: where the solid bars stop is where the money ran out, and any solid bar below that point was funded out of order.
Every funded project ranked above every unfunded one in the committee’s order.
What it means: Here the funding line is one clean cut across the committee’s list.
10
funded
Requested, never ranked
- TC Passios, Abatement Testing Vertex Item#21Town Facilities and Parks · $50,000dropped before ranking
Why: the testing had already been done: an assessment report from the earlier conceptual design was found (remediation costs still to be identified) (meeting recording, captions)
Ranked in: FY2024 rank 20 of 29 (not funded)
- TC Passios Plumbing Upgrade Vertex Item #24Town Facilities and Parks · $20,000dropped before ranking
Why: none recorded (minutes and recordings searched)
Ranked in: FY2024 rank 24 of 29 (not funded)
- Ritter Building, Basement and Foundation RepairTown Facilities and Parks · $20,000dropped before ranking
Why: none recorded (minutes and recordings searched)
Ranked in: never, FY2023 to FY2027
Folded into requests the committee did rank
- Senior Center, Parking LotTown Facilities and Parks · $150,000folded into a ranked request
Why: project split into a design phase and a construction phase; design estimated at $35,000 and given a new number (document)
Ranked in: FY2023 rank 27 of 30 (not funded); FY2024 rank 27 of 29 (not funded); FY2025 rank 32 of 35 (not funded)
- District Schools, Installation of 3M Window Safety FilmSchool Department · $130,000folded into a ranked request
Why: School Committee split the film by building so it could rank Turkey Hill higher (meeting recording, captions)
Ranked in: FY2024 rank 18 of 29 (not funded); FY2025 rank 8 of 35 (funded); FY2025 rank 29 of 35 (not funded); FY2025 rank 30 of 35 (not funded)
What it means: The ranked list is not every request; these never reached it.
3 requests made for FY2025 never reached the ranked list; 1 of 3 have a stated reason.
What it means: The list the committee ranked is what reached it, not every request a department made.
3
requested and never ranked
1 of 3
with a reason a document or recording states
Source [5]
Two orders of one list
What it means: Where the lines cross, the two printed orders disagree about what comes first.
Source [1]
The Town Manager’s rank differed from the committee’s on 19 of 35 requests, by up to 11 places.
What it means: Two printed orders exist for this year; neither alone says what comes first.
19 of 35
requests the two ranks place differently
11
the largest move between the two
Who asked, who got
What it means: A band that narrows was a smaller share of what was funded than of what was requested.
Public Works requested 37.1% of the dollars and received 15.2% of what was funded.
What it means: A share of dollars, not of projects: one large request moves it more than several small ones.
37.1%
Public Works’ share of the dollars requested
15.2%
Public Works’ share of the dollars funded
| Department | Cost | Capital Planning Committee | Town Manager | Members’ average rank | Collins Center score | The department’s own order | Funded | |
|---|---|---|---|---|---|---|---|---|
| Public Safety Radio System - Replace update obsolete equipment- Phase 2 | Fire | $315,263 | 1 | 1 | 2.6 | 35 | 1 | yes |
| Town Wide Keying, Card Access & Alarm System Upgrades | Facilities | $185,000 | 2 | 2 | 4.6 | 43 | 1 | yes |
| Marked Police Vehicle, replacement for K9 cruiser | Police | $92,211 | 3 | 5 | 4.6 | 34 | 1 | yes |
| THES, ADA Study for Renovations and Assessment and Schematic Design | Schools | $275,000 | 4 | 4 | 7.4 | 44 | 2 | yes |
| Marked Police Vehicle, replacement for Traffic vehicle | Police | $73,627 | 5 | 7 | 8.2 | 36 | 2 | yes |
| Library Security Cameras Phase I | IT | $36,000 | 6 | 6 | 9.6 | 41 | 1 | yes |
| Northfield Culvert (Kelly's Pond) Construction | Public Works | $200,000 | 7 | 3 | 9.8 | 44 | 2 | yes |
| THES, Installation of 3M Window Safety Film | Schools | $33,569 | 8 | 8 | 9.8 | 22 | 1 | yes |
| Security Camera Upgrades at Town Buildings | IT | $36,450 | 9 | 9 | 11.6 | 27 | 2 | yes |
| Parks, Wallis Park Basketball and Tennis Courts | Facilities | $70,000 | 10 | 10 | 12.2 | 29 | 6 | yes |
| Funded of requested | Requested | Share of requests | Funded | Share of funded | Its own dollars funded | |
|---|---|---|---|---|---|---|
| Public Works | 1 of 9 | $1,288,500 | 37.1% | $200,000 | 15.2% | 15.5% |
| Schools | 2 of 9 | $883,807 | 25.4% | $308,569 | 23.4% | 34.9% |
| Facilities | 2 of 11 | $715,000 | 20.6% | $255,000 | 19.4% | 35.7% |
| Fire | 1 of 1 | $315,263 | 9.1% | $315,263 | 23.9% | 100.0% |
| Police | 2 of 3 | $199,748 | 5.7% | $165,838 | 12.6% | 83.0% |
| IT | 2 of 2 | $72,450 | 2.1% | $72,450 | 5.5% | 100.0% |
Shares of dollars. Requested means every request the committee’s list holds.
What the documents do not show
Every request each department filed for FY2025, including any never presented or minuted. Closes: each department’s complete request list, requested by records request on 20 November 2026.
Sources
- [1]Capital Planning Committee — FY2025 capital requests by department, final (workbook)
- [2]Town Manager — FY2025-FY2034 preliminary capital plan presentation
- [3]Town of Lunenburg — FY2024 annual town report (Article 6, May 2024)
- [4]Lunenburg Budget Project — capital-rankings.csv, every row and its page or cell
- [5]Lunenburg Budget Project — capital-requests-unranked.csv, every request made and never ranked, with the page, line or second it was read from