Capital planning

FY2026 capital plan

15 of 26 capital requests were funded, 37.7% of the dollars requested.

From ranked to funded

  1. 1Ranked by the Capital Planning Committee

    26 requests · $3,062,742

    Capital Planning Committee — FY2026 final rankings, voted 16 December 2024 (sent by its Chair)

    7 requests ranked here were not in it

  2. 2Option 1, the first of the two options

    19 requests · $1,155,981

    Town of Lunenburg — FY2025 annual town report (FY2026 options, May 2025)

    1 request it left out was added; 5 requests in it were not funded

  3. 3Option 2, voted at Town Meeting

    15 requests · $1,155,981

    Town of Lunenburg — FY2025 annual town report (FY2026 options, May 2025)

Each bar is that stage’s dollars against the ranked total. Stage names are the year’s own documents’.

What it means: The final plan swapped requests in and out of the first one at the same total.

Sources [1][2]

15 of 26 requests were funded, 37.7% of the dollars; the first plan held 19.

What it means: The rest was not cancelled by this vote; the road-back grid on the hub shows which requests came back.

15

funded

26

ranked requests

37.7%

of the requested dollars funded

19

in the first plan

Every request, in rank order

FundedNot funded
  1. 1Patrol CruiserPolice$72,058
  2. The highest-ranked request left unfunded

    2Primary School Feasibility Study for Entry & Drive Way ExpansionSchools$30,000
  3. 3Fire Prevention / Duty Officer VehicleFire$75,000
  4. 4Library HVAC Upgrade and Control DesignFacilities$32,000
  5. 5Town Hall HVAC UpgradesFacilities$113,000
  6. 6Primary School Designer Services, Playground EquipmentSchools$30,000
  7. 7THES Hot Water TankSchools$20,000
  8. 8Senior Center, FlooringFacilities$41,000
  9. 9Teen Center, Replace FloorsFacilities$35,000
  10. 10Public Safety Building 2nd Floor Design – Office/File SpaceFacilities$42,000
  11. 11Patrol CruiserPolice$72,058
  12. 12Town Hall, Window ReplacementFacilities$210,000
  13. 13Compact BackhoePublic Works$115,000
  14. 14Primary School GeneratorSchools$171,896
  15. 15Replacement of Security Camera Central ServerSchools$40,000
  16. 16Senior Center Parking DesignFacilities$32,000
  17. 171 Ton Truck - Utility Body / PlowPublic Works$70,000
  18. 186 Wheel Dump / Spreader / PlowPublic Works$401,000
  19. 19Primary School Window Safety FilmSchools$26,865
  20. 20North Cemetery Expansion Area PrepPublic Works$50,000
  21. 21McNally Park Survey & DesignFacilities$50,000
  22. 22Marshall Pond Weed TreatmentFacilities$50,000
  23. 23Catch Basin Cleaning TruckPublic Works$200,000
  24. 24North Cemetery Roads RepavingPublic Works$225,000
  25. 25Ritter Building Capital SupplementFacilities$712,000
  26. —Primary School Heat Pump System (Local Funding for Green Communities Award)Schools$146,865
One bar a request, as long as its cost; solid bars were funded. Department is our grouping of the project numbers the documents print.

What it means: Read down the list: where the solid bars stop is where the money ran out, and any solid bar below that point was funded out of order.

Sources [1][2]

Option 2 dropped 5 Schools requests costing $146,865 and added one unranked project costing $146,865.

What it means: The Schools dollars in the plan did not change, what they bought did; the report records the vote, not the reason.

$146,865

of Schools requests Option 2 dropped

Requested, never ranked

  • LMHS (Middle-High School) Window Safety FilmSchools · $33,250withdrawn

    Why: Funded instead from ARPA by the Select Board on 13 Nov 2024; the CPC chair then recommended removing ARPA-funded items, and the committee withdrew it from its list on 2 Dec 2024 so it would not compete with unfunded items. (document)

    Ranked in: FY2024 rank 18 of 29 (not funded); FY2025 rank 30 of 35 (not funded)

  • Utility Pickup Truck with PlowSchools · $64,780withdrawn

    Why: Funded instead from ARPA by the Select Board on 13 Nov 2024; the CPC chair then recommended removing ARPA-funded items, and the committee withdrew it from its list on 2 Dec 2024 so it would not compete with unfunded items. (document)

    Ranked in: FY2024 rank 15 of 29 (not funded); FY2025 rank 13 of 35 (not funded)

  • LMHS track and field complex: design and bid solicitation (spring 2025 warrant article)Schools · amount not printedwithdrawn

    Why: Conflicting statements. School department: it pulled the request from the plan because it could not scope even the engineering. Select Board member 18 Mar 2025: it did not rank high enough. Select Board member 1 Apr 2025: the schools pulled it midway, so the CPC never ranked it. (meeting recording, captions)

    Ranked in: never, FY2023 to FY2027

Folded into requests the committee did rank

  • Boys and Girls Club (Teen Center) flooring replacementFacilities · $25,000folded into a ranked request

    Why: none recorded (minutes and recordings searched)

    Ranked in: FY2026 rank 9 of 25 (funded)

  • Exterior repairs at Ritter Memorial BuildingFacilities · amount not printedfolded into a ranked request

    Why: none recorded (minutes and recordings searched)

    Ranked in: FY2026 rank 25 of 25 (not funded)

Requests found in the committee’s minutes, the department and Town Manager decks, the committee’s workbooks and the School Committee’s plans. The departments’ own complete lists are not held, so there may be more. A reason is shown only where a document or a speaker states one.

What it means: The ranked list is not every request; these never reached it.

3 requests made for FY2026 never reached the ranked list; 3 of 3 have a stated reason.

What it means: The list the committee ranked is what reached it, not every request a department made.

3

requested and never ranked

3 of 3

with a reason a document or recording states

Source [4]

Who asked, who got

RequestedFundedFacilities: 43.0% of the requests, 48.0% of the fundedFacilities 43.0%48.0% FacilitiesPublic Works: 34.6% of the requests, 20.3% of the fundedPublic Works 34.6%20.3% Public WorksSchools: 15.2% of the requests, 12.7% of the fundedSchools 15.2%12.7% SchoolsPolice: 4.7% of the requests, 12.5% of the fundedPolice 4.7%12.5% PoliceFire: 2.4% of the requests, 6.5% of the funded6.5% Fire
Shares of dollars. Department is our grouping of the printed project numbers; it matches every department total the year’s documents print.

What it means: A band that narrows was a smaller share of what was funded than of what was requested.

Sources [2][3]

Public Works requested 34.6% of the dollars and received 20.3% of what was funded.

What it means: A share of dollars, not of projects: one large request moves it more than several small ones.

34.6%

Public Works’ share of the dollars requested

20.3%

Public Works’ share of the dollars funded

Every request and every rank
DepartmentCostCapital Planning CommitteeFunded
Patrol CruiserPolice$72,0581yes
Primary School Feasibility Study for Entry & Drive Way ExpansionSchools$30,0002no
Fire Prevention / Duty Officer VehicleFire$75,0003yes
Library HVAC Upgrade and Control DesignFacilities$32,0004yes
Town Hall HVAC UpgradesFacilities$113,0005yes
Primary School Designer Services, Playground EquipmentSchools$30,0006no
THES Hot Water TankSchools$20,0007no
Senior Center, FlooringFacilities$41,0008yes
Teen Center, Replace FloorsFacilities$35,0009yes
Public Safety Building 2nd Floor Design – Office/File SpaceFacilities$42,00010yes
Patrol CruiserPolice$72,05811yes
Town Hall, Window ReplacementFacilities$210,00012yes
Compact BackhoePublic Works$115,00013yes
Primary School GeneratorSchools$171,89614no
Replacement of Security Camera Central ServerSchools$40,00015no
Senior Center Parking DesignFacilities$32,00016yes
1 Ton Truck - Utility Body / PlowPublic Works$70,00017yes
6 Wheel Dump / Spreader / PlowPublic Works$401,00018no
Primary School Window Safety FilmSchools$26,86519no
North Cemetery Expansion Area PrepPublic Works$50,00020yes
McNally Park Survey & DesignFacilities$50,00021no
Marshall Pond Weed TreatmentFacilities$50,00022yes
Catch Basin Cleaning TruckPublic Works$200,00023no
North Cemetery Roads RepavingPublic Works$225,00024no
Ritter Building Capital SupplementFacilities$712,00025no
Primary School Heat Pump System (Local Funding for Green Communities Award)Schools$146,865—yes

Sources [1][2][3]

Each department’s share
Funded of requestedRequestedShare of requestsFundedShare of fundedIts own dollars funded
Facilities8 of 10$1,317,00043.0%$555,00048.0%42.1%
Public Works3 of 6$1,061,00034.6%$235,00020.3%22.1%
Schools1 of 7$465,62615.2%$146,86512.7%31.5%
Police2 of 2$144,1164.7%$144,11612.5%100.0%
Fire1 of 1$75,0002.4%$75,0006.5%100.0%

Shares of dollars. Requested means every request the committee’s list holds.

Sources [2][3]

What the documents do not show

Each department’s own order of its requests. Closes: each department’s FY2026 priority list, requested by records request on 20 November 2026.

Every request each department filed for FY2026, including any never presented or minuted. Closes: each department’s complete request list, requested by records request on 20 November 2026.

Sources [1][2]

Sources

  1. [1]Capital Planning Committee — FY2026 final rankings, voted 16 December 2024 (sent by its Chair)
  2. [2]Town of Lunenburg — FY2025 annual town report (FY2026 options, May 2025)
  3. [3]Lunenburg Budget Project — capital-rankings.csv, every row and its page or cell
  4. [4]Lunenburg Budget Project — capital-requests-unranked.csv, every request made and never ranked, with the page, line or second it was read from

What changed

Version 15 — updated September 20, 2026