FY2026 capital plan
lunenburgbudgetproject.org — written by the Lunenburg Budget Project, an independent tool for residents. Not affiliated with the Town of Lunenburg, the School Committee or the school district. The data this page is computed from: /data/topics/capital-fy2026.json
15 of 26 capital requests were funded, 37.7% of the dollars requested.
From ranked to funded
1Ranked by the Capital Planning Committee
26 requests · $3,062,742
Capital Planning Committee — FY2026 final rankings, voted 16 December 2024 (sent by its Chair)
7 requests ranked here were not in it
2Option 1, the first of the two options
19 requests · $1,155,981
Town of Lunenburg — FY2025 annual town report (FY2026 options, May 2025)
1 request it left out was added; 5 requests in it were not funded
3Option 2, voted at Town Meeting
15 requests · $1,155,981
Town of Lunenburg — FY2025 annual town report (FY2026 options, May 2025)
What it means: The final plan swapped requests in and out of the first one at the same total.
15 of 26 requests were funded, 37.7% of the dollars; the first plan held 19.
What it means: The rest was not cancelled by this vote; the road-back grid on the hub shows which requests came back.
15
funded
26
ranked requests
37.7%
of the requested dollars funded
19
in the first plan
Every request, in rank order
- 1Patrol CruiserPolicePolice$72,058
The highest-ranked request left unfunded
2Primary School Feasibility Study for Entry & Drive Way ExpansionSchoolsSchools$30,000- 3Fire Prevention / Duty Officer VehicleFireFire$75,000
- 4Library HVAC Upgrade and Control DesignFacilitiesFacilities$32,000
- 5Town Hall HVAC UpgradesFacilitiesFacilities$113,000
- 6Primary School Designer Services, Playground EquipmentSchoolsSchools$30,000
- 7THES Hot Water TankSchoolsSchools$20,000
- 8Senior Center, FlooringFacilitiesFacilities$41,000
- 9Teen Center, Replace FloorsFacilitiesFacilities$35,000
- 10Public Safety Building 2nd Floor Design – Office/File SpaceFacilitiesFacilities$42,000
- 11Patrol CruiserPolicePolice$72,058
- 12Town Hall, Window ReplacementFacilitiesFacilities$210,000
- 13Compact BackhoePublic WorksPublic Works$115,000
- 14Primary School GeneratorSchoolsSchools$171,896
- 15Replacement of Security Camera Central ServerSchoolsSchools$40,000
- 16Senior Center Parking DesignFacilitiesFacilities$32,000
- 171 Ton Truck - Utility Body / PlowPublic WorksPublic Works$70,000
- 186 Wheel Dump / Spreader / PlowPublic WorksPublic Works$401,000
- 19Primary School Window Safety FilmSchoolsSchools$26,865
- 20North Cemetery Expansion Area PrepPublic WorksPublic Works$50,000
- 21McNally Park Survey & DesignFacilitiesFacilities$50,000
- 22Marshall Pond Weed TreatmentFacilitiesFacilities$50,000
- 23Catch Basin Cleaning TruckPublic WorksPublic Works$200,000
- 24North Cemetery Roads RepavingPublic WorksPublic Works$225,000
- 25Ritter Building Capital SupplementFacilitiesFacilities$712,000
- —Primary School Heat Pump System (Local Funding for Green Communities Award)SchoolsSchools$146,865
What it means: Read down the list: where the solid bars stop is where the money ran out, and any solid bar below that point was funded out of order.
Option 2 dropped 5 Schools requests costing $146,865 and added one unranked project costing $146,865.
What it means: The Schools dollars in the plan did not change, what they bought did; the report records the vote, not the reason.
$146,865
of Schools requests Option 2 dropped
Requested, never ranked
- LMHS (Middle-High School) Window Safety FilmSchools · $33,250withdrawn
Why: Funded instead from ARPA by the Select Board on 13 Nov 2024; the CPC chair then recommended removing ARPA-funded items, and the committee withdrew it from its list on 2 Dec 2024 so it would not compete with unfunded items. (document)
Ranked in: FY2024 rank 18 of 29 (not funded); FY2025 rank 30 of 35 (not funded)
- Utility Pickup Truck with PlowSchools · $64,780withdrawn
Why: Funded instead from ARPA by the Select Board on 13 Nov 2024; the CPC chair then recommended removing ARPA-funded items, and the committee withdrew it from its list on 2 Dec 2024 so it would not compete with unfunded items. (document)
Ranked in: FY2024 rank 15 of 29 (not funded); FY2025 rank 13 of 35 (not funded)
- LMHS track and field complex: design and bid solicitation (spring 2025 warrant article)Schools · amount not printedwithdrawn
Why: Conflicting statements. School department: it pulled the request from the plan because it could not scope even the engineering. Select Board member 18 Mar 2025: it did not rank high enough. Select Board member 1 Apr 2025: the schools pulled it midway, so the CPC never ranked it. (meeting recording, captions)
Ranked in: never, FY2023 to FY2027
Folded into requests the committee did rank
- Boys and Girls Club (Teen Center) flooring replacementFacilities · $25,000folded into a ranked request
Why: none recorded (minutes and recordings searched)
Ranked in: FY2026 rank 9 of 25 (funded)
- Exterior repairs at Ritter Memorial BuildingFacilities · amount not printedfolded into a ranked request
Why: none recorded (minutes and recordings searched)
Ranked in: FY2026 rank 25 of 25 (not funded)
What it means: The ranked list is not every request; these never reached it.
3 requests made for FY2026 never reached the ranked list; 3 of 3 have a stated reason.
What it means: The list the committee ranked is what reached it, not every request a department made.
3
requested and never ranked
3 of 3
with a reason a document or recording states
Source [4]
Who asked, who got
What it means: A band that narrows was a smaller share of what was funded than of what was requested.
Public Works requested 34.6% of the dollars and received 20.3% of what was funded.
What it means: A share of dollars, not of projects: one large request moves it more than several small ones.
34.6%
Public Works’ share of the dollars requested
20.3%
Public Works’ share of the dollars funded
| Department | Cost | Capital Planning Committee | Funded | |
|---|---|---|---|---|
| Patrol Cruiser | Police | $72,058 | 1 | yes |
| Primary School Feasibility Study for Entry & Drive Way Expansion | Schools | $30,000 | 2 | no |
| Fire Prevention / Duty Officer Vehicle | Fire | $75,000 | 3 | yes |
| Library HVAC Upgrade and Control Design | Facilities | $32,000 | 4 | yes |
| Town Hall HVAC Upgrades | Facilities | $113,000 | 5 | yes |
| Primary School Designer Services, Playground Equipment | Schools | $30,000 | 6 | no |
| THES Hot Water Tank | Schools | $20,000 | 7 | no |
| Senior Center, Flooring | Facilities | $41,000 | 8 | yes |
| Teen Center, Replace Floors | Facilities | $35,000 | 9 | yes |
| Public Safety Building 2nd Floor Design – Office/File Space | Facilities | $42,000 | 10 | yes |
| Patrol Cruiser | Police | $72,058 | 11 | yes |
| Town Hall, Window Replacement | Facilities | $210,000 | 12 | yes |
| Compact Backhoe | Public Works | $115,000 | 13 | yes |
| Primary School Generator | Schools | $171,896 | 14 | no |
| Replacement of Security Camera Central Server | Schools | $40,000 | 15 | no |
| Senior Center Parking Design | Facilities | $32,000 | 16 | yes |
| 1 Ton Truck - Utility Body / Plow | Public Works | $70,000 | 17 | yes |
| 6 Wheel Dump / Spreader / Plow | Public Works | $401,000 | 18 | no |
| Primary School Window Safety Film | Schools | $26,865 | 19 | no |
| North Cemetery Expansion Area Prep | Public Works | $50,000 | 20 | yes |
| McNally Park Survey & Design | Facilities | $50,000 | 21 | no |
| Marshall Pond Weed Treatment | Facilities | $50,000 | 22 | yes |
| Catch Basin Cleaning Truck | Public Works | $200,000 | 23 | no |
| North Cemetery Roads Repaving | Public Works | $225,000 | 24 | no |
| Ritter Building Capital Supplement | Facilities | $712,000 | 25 | no |
| Primary School Heat Pump System (Local Funding for Green Communities Award) | Schools | $146,865 | — | yes |
| Funded of requested | Requested | Share of requests | Funded | Share of funded | Its own dollars funded | |
|---|---|---|---|---|---|---|
| Facilities | 8 of 10 | $1,317,000 | 43.0% | $555,000 | 48.0% | 42.1% |
| Public Works | 3 of 6 | $1,061,000 | 34.6% | $235,000 | 20.3% | 22.1% |
| Schools | 1 of 7 | $465,626 | 15.2% | $146,865 | 12.7% | 31.5% |
| Police | 2 of 2 | $144,116 | 4.7% | $144,116 | 12.5% | 100.0% |
| Fire | 1 of 1 | $75,000 | 2.4% | $75,000 | 6.5% | 100.0% |
Shares of dollars. Requested means every request the committee’s list holds.
What the documents do not show
Each department’s own order of its requests. Closes: each department’s FY2026 priority list, requested by records request on 20 November 2026.
Every request each department filed for FY2026, including any never presented or minuted. Closes: each department’s complete request list, requested by records request on 20 November 2026.
Sources
- [1]Capital Planning Committee — FY2026 final rankings, voted 16 December 2024 (sent by its Chair)
- [2]Town of Lunenburg — FY2025 annual town report (FY2026 options, May 2025)
- [3]Lunenburg Budget Project — capital-rankings.csv, every row and its page or cell
- [4]Lunenburg Budget Project — capital-requests-unranked.csv, every request made and never ranked, with the page, line or second it was read from